Technical note
Side-stream flow is not a guessed percentage: size from scaling rate, solids load and equipment hydraulics, then take the largest.
“How much side-stream flow do I need?” It is the first question when adding electrochemical treatment or side-stream filtration. The answer is not a percentage; it is the largest of three constraints: scaling rate, suspended-solids load, and the equipment's own flow window.
The amount of scale formed depends on the calcium, magnesium and alkalinity entering with make-up water, and on the cycles of concentration. Convert make-up calcium hardness and total alkalinity to calcium carbonate equivalent, multiply by make-up flow and the system's retention, and you get the mass of scale-forming material entering per day. The side-stream treatment capacity must exceed that mass, otherwise scale still accumulates on heat-transfer surfaces. The first step is therefore not choosing a flow but calculating water quality and quantity.
A cooling tower is a natural scrubber: dust, micro-organisms and algae enter with air. Side-stream filtration and electrochemical treatment together determine how clean the circulating water can stay. Turbidity, suspended solids and heterotrophic plate count are three measurable indicators. If make-up turbidity is high or the tower sits in a dusty area, the side-stream ratio must be higher; removing scale but not mud still leaves exchangers fouled.
Electrochemical equipment has rated flow and residence-time requirements. Too little flow means low efficiency; too much means insufficient treatment per pass. Selection must consider side-stream pump head and piping resistance, the location of take-off and return points (to avoid short-circuiting), and the equipment's allowable inlet temperature and pressure. Many site failures are not equipment failures: the take-off sits in a dead zone and treated water returns next to the suction.
Side-stream flow is usually expressed as a percentage of circulating flow, but the number varies with water quality and duty. We deliberately do not quote a universal percentage here, because it would mislead. The correct method: calculate the minimum treatment flow from the scaling rate, add a margin for suspended solids, then verify piping and pump capacity hydraulically — and take the largest of the three. If the three differ widely, the system needs another fix first (additional filtration or a make-up change).
We need the four make-up water numbers, circulating flow, cycles of concentration, tower type and surroundings, and details of any existing side-stream equipment. We will work through the sequence above and give the recommended side-stream flow, take-off and return locations, and the assumptions behind the check — not a single number claimed to fit everything.
Want this calculated for your plant?
Send the cooling tower rated flow and your make-up water analysis (calcium hardness / total alkalinity / chloride / TDS) and we will issue a selection report with the assumptions stated.
Request a calculation Technical FAQ
This note covers method and limits only; no unverified case data is quoted.